GPC field-to-GIS workflow

Control the evidence before the trench is closed.

A reliable GPC workflow starts with the required handover and survey responsibility, then works backwards to positioning, image coverage, processing and quality checks.

Use this sequence to coordinate the contractor, surveyor, asset owner and processing team. It does not replace the governing specification or professional judgement.

00

Scope, requirements and survey responsibility

Confirm whether this is an information-only GPC record, a contractor evidence package, a client-required GPC, an as-built utility survey or a trial-trench utility survey governed by SLA standards. Determine the required Registered Surveyor’s involvement before data acquisition. Establish site access, safe trench-edge working arrangements, intended capture timing and any security restrictions on cloud processing.

Project scoping inputs: site and trench plan; asset type; visible components; schedule to backfill; survey specification and scope; client GIS schema; permitted processing location; required output formats; expected review and sign-off process.

01

Establish positioning and control

Plan the reference framework for horizontal and vertical coordinates. For Singapore projects, discuss SVY21 projected grid coordinates (EPSG:3414), Singapore Height Datum (SHD) and use of SGEOID09 where relevant. Do not assume a device’s ellipsoidal height is already a valid SHD level. Check compatibility and transformation steps.

RTK corrections may be supplied by a compatible reference network such as SLA’s SiReNT or another verified source. Record the correction service and status, equipment setup, antenna/phone geometry and unreliable GNSS reception. For close-range photogrammetry under SLA Version 1.3, section 4.4 specifies at least four GCPs distributed around the trench/utilities, visible in the imagery and surveyed by a Registered Surveyor. RTK-tagged imagery without dedicated GCPs may suit other documentation purposes, but must not be presented as automatically satisfying this requirement.

02

Capture exposed utility surfaces

Use PIX4Dcatch with a compatible smartphone and a supported RTK receiver where applicable. Capture systematic overlapping views of the trench edge, pipe tops, bends, tees, branches, fittings, chamber openings and relevant surrounding ground features. For regulated close-range photogrammetry under SLA Version 1.3, the photographic procedure specifies at least 80% overlap between successive images.

Before leaving site, check that critical surfaces and GCPs are clearly visible, images are sharp, lighting is adequate and there are no gaps around crossings or utility interfaces. Do not infer geometry hidden by soil, water, machinery or other pipes.

03

Process into a georeferenced 3D record

Process a supported PIX4Dcatch capture in PIX4Dmatic for local desktop processing or PIX4Dcloud for an authorised cloud workflow. Import required control and checkpoints and select the correct project reference system. Generate the agreed point-cloud, model and related products. Inspect alignment, poorly reconstructed surfaces, image coverage and possible coordinate or height inconsistencies.

Choose processing mode deliberately. Cloud processing offers sharing convenience but may not be approved for sensitive sites. Desktop processing can support projects where local handling is preferred, subject to licensing, hardware and security rules. Do not upload government or critical-infrastructure data without the data owner’s permission.

04

Validate before vectorisation

Use the agreed survey control/checkpoint framework to assess the model. Record independent check results where available, separately for eastings, northings and levels; identify missing or obscured geometry. The ±100 mm horizontal and vertical absolute-accuracy figure in SLA’s utility-survey standard is a project survey requirement—not a blanket promise that every mobile capture meets it.

Minimum QA record: project ID, site/date, operator and Registered Surveyor as applicable, hardware/software versions, control/GCP/checkpoint references, correction source, coordinate and height transformation, method used, coverage exclusions, signed-off acceptance criteria and measured/checkpoint residuals when available.

05

Extract actual asset geometry

Use PIX4Dsurvey or Global Mapper to digitise required real-world utility features from suitable 3D data. Distinguish top of utility, centreline, invert, trench boundary and ground level. Do not label a pipe centreline when only the visible top-of-pipe has been measured unless diameter/offset and the derivation method are explicitly recorded and accepted.

Identify asset type and source, then map features into the client or current SLA GIS schema as appropriate. For the Version 1.3 submission framework, pipes, cables and drains classified as lines are GIS 3D Line features with X/Y/Z in geometry. Relevant structure points use X/Y in point geometry with specified elevation values in attributes. Consult the exact appendix for mandatory attribute names and allowed values.

06

Package and hand over

Prepare the agreed SHP file set or geodatabase, coordinate metadata, QA summary, field evidence and any GPC/mesh deliverables the contract requires. Validate that the recipient can open the data and that 3D geometries and elevation values survive export. A single .shp file alone is not a portable Shapefile dataset: include the companion files.

For GIS submission under the current SLA standard, use SHP or GDB as specified and ensure the Registered Surveyor workflow is complete. The finished deliverable is useful only when its location, geometry, provenance, attributes and limitations are understandable to the next person.

Capture decisions

Record the opening conditions, not only the attractive model.

A visually complete mesh can still hide an unusable survey observation. The field and office teams need a common record of what was visible, positioned and independently checked.

  • Opening, exposure and backfill sequence
  • Safe camera positions and stable lighting
  • Texture, reflections, water and moving machinery
  • GNSS status, correction source and control observations
  • Occluded areas, diameter assumptions and feature definitions
  • Independent check observations and exceptions
Manufacturer illustration of overlapping image capture positions around a site
Manufacturer workflow illustration · Coverage alone does not establish accuracy

Regulated survey interface

SLA close-range photogrammetry: plan the actual requirements.

For relevant work under SLA’s October 2025 Version 1.3, the method includes specific capture, control, accuracy and data-output requirements. The following summary is not a substitute for the full document.

Requirement areaWorkflow implication
Photography

At least 80% overlap between successive images, with the specified exposure and capture conditions.

Ground control

At least four GCPs, evenly distributed around the trench/utilities, visible in imagery and surveyed by a Registered Surveyor.

Professional supervision

Relevant new as-built and trial-trench utility surveys require direct Registered Surveyor supervision and observations before backfilling.

Absolute accuracy

±100 mm horizontally and vertically is a survey requirement to demonstrate, not a generic product specification.

GIS representation

Relevant utility lines use 3D Line geometry with X/Y/Z; structure points use X/Y with specified elevation attributes.

Submission

SHP or GDB as specified. A lone .shp file is not a complete portable Shapefile dataset.

Open SLA Version 1.3 (PDF)

Where methods differ

GPC does not replace subsurface detection.

Photogrammetry / GPC

Reconstructs visible exposed surfaces. Useful for trench documentation and subsequent geometry extraction.

GPR / EML and other surveys

Used for applicable concealed-utility investigation under their own procedures, limitations and quality requirements.

Registered Surveyor

Directs and takes professional responsibility for relevant regulated observations, control and submission scope.

Manufacturer walkthrough

Review the field-to-office sequence.

PIX4Dcatch underground utility scanning workflow

Manufacturer demonstration of mobile capture, RTK integration and downstream processing. Project-specific controls and acceptance checks still apply.

Watch on YouTube Representative manufacturer visual. Video loads only after you select play.
RTK availability is not continuous by assumption.

Trench walls, buildings and canopy can obstruct satellite signals or introduce multipath. Confirm the correction source and positioning plan for the actual site. Never request or send NTRIP passwords or subscription tokens through a general enquiry form.

Plan before the excavation window

Plan the control, capture and handover as one scope.

Tell us the opening window, required outputs and whether a Registered Surveyor is already appointed.

Discuss GPC